Path: utzoo!utgpu!jarvis.csri.toronto.edu!rutgers!tut.cis.ohio-state.edu!ucbvax!agate!eos!ames!trident.arc.nasa.gov!yee From: yee@trident.arc.nasa.gov (Peter E. Yee) Newsgroups: sci.space.shuttle Subject: Shuttle Status for 06/27/89 (Forwarded) Message-ID: <27682@ames.arc.nasa.gov> Date: 28 Jun 89 00:40:55 GMT Sender: usenet@ames.arc.nasa.gov Reply-To: yee@trident.arc.nasa.gov (Peter E. Yee) Organization: NASA Ames Research Center, Moffett Field, CA Lines: 66 KSC SPACE SHUTTLE PROCESSING REPORT - TUESDAY, JUNE 27, 1989 STS-28 - COLUMBIA (OV 102) - OPF BAY 1 Shuttle managers met yesterday and today in a routine pre- launch meeting to discuss the readiness of the orbiter Columbia for its move to the Vehicle Assembly Building. After considering the amount of work left on Columbia, the target date for transferring Columbia to the VAB was moved to no earlier than Saturday, July 1, at 12 noon. Management will meet again on Friday to discuss the remaining work, including tile, and the status of the investigation of the main engine test firing incident at Stennis Space Center, Mississippi last Friday. All shuttle program elements were commended for the significant amount of work completed on Columbia to date. Tonight, technicians are scheduled to replace two electronic boxes in Columbia. One of the boxes, called a motor control assembly (MCA), sends commands to the orbiter's vent doors, external tank doors and orbital maneuvering system crossfeed valves. In addition, the MCA relays information about the position of those systems to the orbiter's cockpit. The MCA experienced internal blown fuse link. An electronic box, located in middeck, for the pilot's heads up display (HUD) will be removed tonight because of an intermittent lighting problem. Retest of both components is scheduled. A positive pressure structural leak test of the aft compartment is planned tonight. Preparations are continuing for a frequency response test of the orbiter's aerosurfaces this week. Technicians are continuing to bond tiles, install gap fillers and fit and install thermal blankets on the payload bay doors. Technicians finished painting the name Columbia on the left and right forward fuselage today and will finish painting the flag tonight. STS-34 - ATLANTIS (OV 104) - OPF BAY 2 Preparations are underway to install tires on the main landing gear this week. Testing of the right orbital maneuvering system pod is scheduled to begin tonight. Coolant lines were recently installed for the radioisotope thermoelectric generators (RTGs), used to power the Galileo spacecraft, and leak checks are planned this week. Orbiter systems will be tested this week. STS-33 - DISCOVERY (OV 103) - OMRF Power down work and modifications continue this week in the forward, mid and aft sections of the orbiter. Discovery will be transferred to bay 1 shortly after Columbia is moved to the VAB. STS-28 SOLID ROCKET BOOSTERS - VAB Closeouts of the boosters and tank are underway in preparation for mating with the orbiter Columbia. STS-34 SOLID ROCKET BOOSTERS - VAB/RPSF Technicians are preparing the right aft booster for stacking on the mobile launcher platform. Meanwhile, the last three right hand segments are being readied for stacking in the RPSF.