Path: utzoo!utgpu!news-server.csri.toronto.edu!cs.utexas.edu!swrinde!elroy.jpl.nasa.gov!ames!trident.arc.nasa.gov!yee From: yee@trident.arc.nasa.gov (Peter E. Yee) Newsgroups: sci.space.shuttle Subject: Shuttle Status for 02/08/91 (Forwarded) Message-ID: <1991Feb8.174048.14540@news.arc.nasa.gov> Date: 8 Feb 91 17:40:48 GMT Sender: usenet@news.arc.nasa.gov (USENET Administration) Reply-To: yee@trident.arc.nasa.gov (Peter E. Yee) Organization: NASA Ames Research Center, Moffett Field, CA Lines: 68 KSC SHUTTLE STATUS REPORT - FRIDAY, FEB. 8, 1991 STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1 LAUNCH - MARCH 1991 WORK IN PROGRESS: - Orbiter weight and center of gravity determination. - Vehicle closeouts in preparation for transfer to the VAB. WORK COMPLETED: - Positive pressure structural leak test of the aft compartment. - Troubleshooting of the heater for a thruster on the right orbi- tal maneuvering system pod revealed that the heater is good. The problem has been isolated to a cable harness routed between the logic control assembly and the thruster. More troubleshooting work will be performed in the Vehicle Assembly Building once ac- cess to the aft compartment can be obtained. WORK SCHEDULED: - Attaching the orbiter to the transporter. - Rollover to the Vehicle Assembly Building tomorrow afternoon and mate to the external tank. STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - OPF BAY 2 LAUNCH - APRIL 1991 WORK IN PROGRESS: - Water spray boiler leak and functional tests. - Main engine 2 flight readiness test. - Functional tests of the forward reaction control system. - Preparations to install the left orbital maneuvering system pod. - Tests of the right orbital maneuvering system pod. WORK COMPLETED: - Landing gear functional tests. - Checks of the closed circuit television system. WORK SCHEDULED: - Crew Equipment Interface Test this weekend. - Installation of the left orbital maneuvering systems pod Satur- day night. STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - VAB HB 2 LAUNCH - MAY WORK SCHEDULED: - Transfer to the Orbiter Processing Facility several hours after Discovery's move to the VAB. STS-39 BOOSTERS/TANK - VAB WORK COMPLETED: - Retraction of platforms away from the boosters and tank. - Preparations to mate the external tank and solid rocket boosters with the Orbiter Discovery. WORK SCHEDULED: - Mating the orbiter to the external tank this weekend. - Shuttle Interface Test next week. - Rollout to Launch Pad 39-A targeted for Feb. 15.