Newsgroups: sci.space.shuttle Path: utzoo!utgpu!news-server.csri.toronto.edu!rpi!zaphod.mps.ohio-state.edu!think.com!ames!usenet From: yee@trident.arc.nasa.gov (Peter E. Yee) Subject: Shuttle Status for 04/19/91 (Forwarded) Message-ID: <1991Apr22.014200.4520@news.arc.nasa.gov> Sender: usenet@news.arc.nasa.gov (USENET Administration) Organization: NASA Ames Research Center, Moffett Field, CA Date: Mon, 22 Apr 91 01:42:00 GMT KSC SHUTTLE STATUS REPORT - FRIDAY, APR. 19, 1991 - 10 a.m. STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A LAUNCH - APRIL 23 WORK IN PROGRESS: - Launch countdown preparations. - Removal of service platforms from the deck of the mobile launcher platform (MLP). - Removing handrails from the launch platform. - Preparing the MLP hazardous gas detection system for launch. - Removal of protective covers from the orbiter's reaction con- trol system thrusters. - Removing platforms from the crew cabin. - Payload servicing operations. WORK COMPLETED: - Pressurization of the hypergolic propellant system for flight. - Purging of the power reactant storage and distribution system for flight. - Check of a purge duct clamp in the aft compartment. Aft is closed out for flight WORK SCHEDULED: - Final payload preparations. - Launch countdown begins at 8:45 a.m. EDT Saturday, April 20. - Closing the payload bay doors for flight Sunday. - STS-39 flight crew arrival at 6:30 p.m. EDT Saturday. - Launch at 7:05 a.m. EDT Tuesday, April 23. STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1 LAUNCH - MAY WORK IN PROGRESS: - Thermal protection system operations. - Closing the aft compartment for transfer to the VAB. - Cleaning the payload bay. - Close the payload bay doors. - Leak checks of the crew cabin. WORK SCHEDULED: - Leak tests of the Spacelab payload this weekend. - Tow to the Vehicle Assembly Building targeted for April 24. STS-43 - ATLANTIS (OV 104) - OPF BAY 2 WORK IN PROGRESS: - Jacking and leveling the orbiter in the processing facility. - Gaining access to the vehicle. - Preparing to power up the orbiter. - Removal of ferry kit items. WORK COMPLETED: - Demated from the 747 just before midnight. - Tow to the OPF started at about 5 a.m. this morning. WORK SCHEDULED: - Opening the payload bay doors this weekend. - Removal of the tail cone on Monday. STS-40 SOLID ROCKET BOOSTERS - VAB WORK IN PROGRESS: - Routing cables between the tank and boosters and launch plat- form. - Closing out the solid rocket booster field joints for flight. WORK SCHEDULED: - Mating the Shuttle Columbia to the external tank next week.