Newsgroups: sci.space.shuttle Path: utzoo!utgpu!news-server.csri.toronto.edu!rpi!think.com!news.arc.nasa.gov!usenet From: yee@trident.arc.nasa.gov (Peter E. Yee) Subject: Shuttle Status for 06/24/91 (Forwarded) Message-ID: <1991Jun24.225516.18901@news.arc.nasa.gov> Sender: usenet@news.arc.nasa.gov (USENET Administration) Organization: NASA Ames Research Center, Moffett Field, CA Date: Mon, 24 Jun 91 22:55:16 GMT KSC SHUTTLE STATUS - MONDAY, JUNE 24, 1991 -- 11:00 a.m. _________________________________________________________________ STS-43/TDRS-E - ATLANTIS (OV 104) - VAB LAUNCH -- LATE JULY WORK IN PROGRESS: * Preparations for rollout to Pad 39-A scheduled for 12:01 a.m. Tuesday * Retract platforms * Pad 39-A preparations for receiving shuttle vehicle * Final TDRS payload fuel servicing at pad WORK COMPLETED: * Orbiter/external tank electrical connections * SRB joint heater inspections * Vehicle power up operations WORK SCHEDULED: * 8:00 p.m. Call to Stations for rollout * Rollout to Pad 39-A STS-48/UARS -- DISCOVERY (OV 103) - OPF BAY 1 LAUNCH SEPTEMBER/OCTOBER WORK IN PROGRESS: * Bulb seal repair work * Payload bay reconfiguration * Helium tank leak checks * Radiator inspections * Robot arm tests * Auxiliary Power Unit leak and functional tests WORK COMPLETED: * Ammonia boiler servicing * On board fuel cell system tests * OMS system functional checks * Flight control inspections * Nose wheel steering checkouts WORK SCHEDULED: * Payload bay door functional tests STS-49 -- ENDEAVOUR (0V 105) -- VAB High Bay 2 WORK IN PROGRESS: * 17 inch disconnect checks * Aft compartment cleaning * Thermal Protection System work * Ammonia boiler installation checks * External tank door housing mechanical checks STS-40/SLS-1 -- COLUMBIA (OV 102) -- OPF Bay 2 WORK IN PROGRESS: * Preps for tailcone removal * Work platform configuration WORK COMPLETED: * Arrived at KSC's Shuttle Landing Facility at 8:59 a.m. last Friday. * Demated from Shuttle Carrier Aircraft and towed to OPF early Saturday morning * Jack and level operations * Payload bay door strongback installation * Post mission propellant deservicing WORK SCHEDULED: * Vehicle power up * Open payload bay doors * Inspections of payload bay door bulb seal * Remove from payload bay the Spacelab Life Sciences module