Autzoo.852 general utzoo!henry Wed Aug 5 15:31:39 1981 renovation progress The work in 336 is moving along fairly well. The lights and electrical odds and ends have been removed to clear the way for construction. The overhead service clusters, the unwanted lab benches, and the unwanted plumbing are being ripped out at this very moment. The frame for the partition wall is in place although not entirely complete, as is the frame for the door in it. The materials for the actual construction of the wall appear to be present, so the construction end of things is moving well. The only hassle at the moment is that the installation of the new cable troughs may be held up by a shortage of cable trough. Overall, things are going well.